New Building Update – July 28 2009

Over the past couple of months there has been a lot of activity on the construction site.  In June the general contractor was able to get the office and warehouse slabs built.  In July they have been focusing on building the concrete panel walls for the building.  As of today all of those panels are complete and they are starting the assembly process of the new facility.

Here are some of the pictures from the first couple of walls being put into place:

Panel 1 Being Placed

The above shows panel #1 in place and being braced up until the roof structure is in place.
The picture below shows panel #2 being lifted off the warehouse slab.

Panel 2 off slab

This last picture shows the crew guiding the 2nd panel into place on to the wall footings.

Panel 2 guide

More pictures and information will be posted as the facility progresses.